Documents
October 2022 Final DSR
- Design Study Report
- Appendix A: 2016 FLAP Application
- Appendix B: 2012 Whittier Comprehensive Plan Update
- Appendix C: Final Geotechnical Engineering Report – Part 1
- Appendix C: Final Geotechnical Engineering Report – Part 2
- Appendix D: Environmental Gap Analysis
- Appendix E: Draft DSR Conceptual Engineer’s Estimate
- Appendix F: Draft DSR Plan & Profile and Cross Sections
- Appendix G: 95% Design Plans and Cross Sections – Part 1
- Appendix G: 95% Design Plans and Cross Sections – Part 2
- Appendix G: 95% Design Plans and Cross Sections – Part 3
- Executive Summary
April 2022 Signed US Army Corps of Engineers Permit
June 2021 Signed Finding of No Significant Impact (FONSI)
April 2021 Conceptual Recreation Plan
March 2021 Signed Environmental Assessment
- Complete Environmental Assessment
- Executive Summary
- Chapter 1 – Purpose and Need for Action
- Chapter 2 – Alternatives Including the Proposed Action
- Chapter 3 – Affected Environment and Environmental Consequences
- Chapter 4 – Irreversible or Irretrievable Commitment of Resources
- Chapter 5 – Summary of Mitigation Measures
- Chapter 6 – Required Permits and Approvals
- Chapter 7 – Coordination and Consultation
- Chapter 8 – References
- Appendix A – U.S. Department of Transportation Act Section 4(f) Coordination
- Appendix B – Essential Fish Habitat and Fish Surveys
- Appendix C – Endangered Species Act Section 7 Consultation and Coordination
- Appendix D – National Historic Preservation Act Section 106 Consultation and Coordination
- Appendix E – Visual Impact Assessment
- Appendix F – Public and Agency Consultation and Coordination
January 28, 2020 Public Open House
January 8, 2019 Public Open House
August 2018 Draft DSR
- Whole Document Part 1
Whole Document Part 2 - Report
- Appendix A: 2016 Federal Land Access Program Application
- Appendix B: Excerpts from the 2012 Whittier Comprehensive Plan Update
- Appendix C: Preliminary Geotechnical Engineering Report
- Appendix D: Environmental Data Gap Analysis
- Appendix E: Conceptual Engineer’s Estimate
- Appendix F: Roadway Plan & Profile and Cross Sections
April 11, 2018 Public Open House
Timelines
Summer 2022
Completed 95% Plans, Spes, & Estimate
Summer 2021
Signed Finding of No Significant Impact Initiated Permitting Phase
Winter 2020/2021
Completed 65% Plans, Specs, & Estimate
Finalized Draft EA
Summer/Fall 2020
Completion of Cultural Resources, Survey, and Geotech Field Work
Design of Recreational Facilities
Winter 2019/2020
January 2020 Project Update and Proposed Alternative Public Scoping Open House
Summer/Fall 2019
Survey and Geotech Field Work Initiated
Additional Fish and Cultural Resources Field Studies Conducted
Design of Trinity Point Terminus and Access Roads
Winter 2018/2019
January 2019 Draft Design Study Report Public Open House
Summer/Fall 2018
Draft DSR Completed
Fish and Cultural Resources Field Work Initiated
Spring 2018
April 2018 Project Introduction Public Open House
Pre-National Environmental Policy Act Scoping Conducted and Alternatives Considered